pl.ID programme's milestones

ikona

March 1, 2015

The launch of the pl.ID programme – currently running system will be switched off

strzałka w górę

ikona

July 2014 – February 2015

Functional and non-functional testing of new systems
End-users and system administrators trainings
Retrofitting of territorial units with the necessary equipment

strzałka w górę
ikona

October 2013 – October 2014

Programming and development tasks

strzałka w górę
ikona

February 2013 – June 2014

Modernization of a central infrastructure at the main servers

strzałka w górę
ikona

February 2013 – December 2013

Conceptual work, the preparation of analysis and technical documentations

strzałka w górę
ikona

February 2013

Signing of the agreement between the Ministry of Interior and COI for the pl.ID programme